400 George St, Sydney NSW

Client
Forge Venture Management | Mirvac

Project Type
Construction

Completed
2026

Location
Sydney, NSW

Sector
Commercial

Duration
16 weeks

Project Overview

This project delivered a multi level refurbishment and services upgrade across Levels 28, 29 and 30 at 400 George Street, Sydney. Works included full strip outs, tenancy reconfiguration, cold shell reinstatement and complete spec fit out delivery. The project was completed within a live commercial building with careful staging to maintain uninterrupted operations.

ATG delivered a comprehensive refurbishment and services upgrade across Levels 28, 29 and 30 at 400 George Street for Mirvac under a Design and Construct contract. The scope combined tenancy reconfiguration, cold shell reinstatement and a full spec fit out, along with upgrades to lobby and bathroom amenities on all levels.

Level 28 involved a complete strip out of the existing tenancy followed by subdivision into two new tenancies, T1 and T2. This level also received new lobby and bathroom upgrades. Level 29 was stripped back and returned to a cold shell condition, reinstating services to base building requirements and aligning lobby and bathroom finishes with the building standard. Level 30 received a full strip out and delivery of a complete spec fit out across the entire floor, supported by coordinated services upgrades and amenity improvements.

The project was delivered within a fully operational commercial building. Works were staged to maintain separation between construction and occupied areas, with high impact activities completed after hours to avoid disruption. ATG coordinated closely with multiple contractors working concurrently in the building, supported by regular interface meetings and detailed programme sequencing.

Key challenges included tenancy interfaces, access constraints, limited loading dock availability and the need to modify and reinstate services without affecting live operations. These were managed through advance stakeholder communication, defined access routes, strict site controls and coordinated shutdown planning. A weekly delivery schedule was implemented to optimise logistics and reduce congestion.

Quality and consistency across the three levels were maintained through robust ITP processes, trade coordination and regular inspections. Safety systems were supported by digital platforms for inductions and permit management, daily pre starts and ongoing site audits. Additional supervision was allocated during critical activities to ensure coverage across multiple work fronts.