New Farm Community Centre, New Farm QLD

Client
Department of Housing and Public Works

Project Type
Construction

Completed
2020

Location
New Farm, QLD

Sector
Public

Duration
25 Weeks

Project Overview

ATG partnered with Communify and Department of Housing and Public Works to provide significant expansion and upgrade works to the New Farm Neighbourhood Centre. 

Construction included a house lift and new ground floor, which was carried out in five stages with overlaps to ensure the critical completion date was achieved.
A major consideration for this project was ensuring the new house was DDA compliant, enhancing the aesthetics of the house, enhancing the functionality of the house, installing a new commercial kitchen and grease trap whilst providing more facilities for the members of the public.